§ 29-148. Permanent pavement repairs.  


Latest version.
  • All permanent pavement repairs shall be made under one (1) of the two (2) following methods:

    (1)

    Permanent pavement repairs by city. If the city is to make the permanent pavement repairs, the ROW user shall maintain the excavated area for a period of two (2) weeks after acceptance by the director. After the two-week period, the city will be responsible for maintaining the excavated area until final restoration is made. Backfill failures shall remain the responsibility of the ROW user. The ROW user shall reimburse the city for all costs of any backfill failure before and/or after permanent pavement repair.

    (2)

    Permanent pavement repairs by ROW user. If the ROW user is authorized to make permanent pavement repairs, the ROW user will maintain the excavated area until permanent pavement restoration of the excavated area is complete. The ROW user shall make final repairs within thirty (30) days on arterial and collector streets and within thirty (30) days on residential, local and alley streets after the director makes final inspection. Backfill failures shall remain the responsibility of the ROW user.

(Ord. No. 93319, § 1, 1-25-01)