§ 35-455. Demolition Permit Applications.  


Latest version.
  • (a)

    Applicability. The provisions of this section apply to any application for demolition of a historic landmark (section 35-614 of this chapter). The provisions of this section apply to any historic landmark or any property located within a historic district.

    (b)

    Initiation.

    (1)

    Historic Landmarks and Contributing Properties. The applicant shall submit all necessary materials to the historic preservation officer, hereafter referred to as the HPO, at least fifteen (15) days prior to the HPO hearing in order that staff may review and comment and/or consult on the case. Staff and/or professional comments shall be forwarded to the HPO for consideration and review and made available to the applicant for consideration prior to the hearing. The HPO may require that an applicant furnish such additional information that is relevant to its determination of unreasonable economic hardship and may require that such additional information be furnished under seal. The HPO or its agent may also furnish additional information as the HPO believes is relevant. The HPO shall also state which form of financial proof it deems relevant and necessary to a particular case. In the event that any of the required information is not reasonably available to the applicant and cannot be obtained by the applicant, the applicant shall file with his affidavit a statement of the information which cannot be obtained and shall describe the reasons why such information cannot be obtained.

    (2)

    Other Demolition Permits. All applications for permits to demolish buildings, objects, sites, or structures which are not historic landmarks, contributing properties, or an intrusion in the district shall be referred to the city HPO for the purpose of determining whether or not the building, object, site, or structure may have historical, cultural, architectural, or archaeological significance.

    (c)

    Completeness Review. The historic preservation officer shall review the demolition permit application for completeness in accordance with subsection 35-451(c) of this chapter. The appellate agency for purposes of completeness review (see subsection 35-402(c) of this chapter) shall be the historic and design review commission.

    (d)

    Decision.

    (1)

    Historic Landmarks. Whenever an application for a certificate regarding the demolition of a landmark is submitted to the historic and design review commission, the historic and design review commission shall not hold a public hearing on the application for sixty (60) days from the date the application is received by the office of historic preservation. This time period is intended to permit the city historic preservation officer to discuss the proposed demolition informally with the property owner, other city officials, registered neighborhood associations, and local preservation organizations, to see if an alternative to demolition can be found before a formal consideration of the application by the historic and design review commission. At least one meeting with the registered neighborhood association shall occur within this period if the proposed demolition is located within a historic district. The historic preservation officer shall prepare, as a part of the submission, a report to the historic and design review commission analyzing alternatives to demolition, and request from other city departments or agencies information necessary for the preparation of this report.

    If within this sixty-day period any one (1) of the following three (3) events shall occur, the historic and design review commission may defer hearing the application for six (6) months and it shall be considered to have been withdrawn by the applicant during such six-month period:

    • The owner shall enter into a binding contract for the sale of the property,

    • Approved arrangements shall be made for the structure to be moved to an approved new location, or

    • The City of San Antonio shall determine to condemn the property and take it by the power of eminent domain for rehabilitation or reuse by the city or other disposition with appropriate preservation restrictions in order to promote the historic preservation purposes of this chapter to maintain the structure and protect it from demolition.

    If within the sixty-day period none of the three (3) events summarized above shall have occurred, the historic and design review commission shall schedule a hearing on the demolition application at its next regularly scheduled meeting following the expiration of the sixty-day period, shall request all knowledgeable parties to comment at the hearing on the proposed demolition, and shall make its written recommendation within thirty (30) days after hearing the request for demolition. The historic and design review commission shall also request the city engineer or a third-party consultant to prepare a report on the state of repair and structural stability of the structure for which an application to demolish has been filed. This report shall be presented to the city HPO prior to the date of the historic and design review commission's hearing on the demolition permit application, and shall become part of the administrative record on the application.

    (2)

    Other Demolition Permits. If the property is not a historic landmark, contributing property, or an intrusion in the district, the historic preservation officer shall determine whether or not the building, object, site, or structure may have historic, cultural, architectural, or archaeological significance within thirty (30) days after receipt of the completed application. In making this determination, the historic preservation officer shall apply the appropriate definitions in appendix A of this chapter, as well as any applicable standards or guidelines adopted by the city council. If the building, object, site, or structure is determined to have no cultural, historical, architectural, or archaeological significance, a demolition permit may be issued immediately, provided such application otherwise complies with the provisions of the demolition ordinance and all city code requirements. If the building, object, site, or structure is found to have significance and is determined to an eligible resource for historic designation in accordance with this section, the historic preservation officer shall notify the owner of the property in writing of such determination in accordance with this division. The historic preservation officer shall retain a written statement summarizing the reasons for their determination for such period as required under applicable record retention laws as followed by the city clerk's office. The historic preservation officer shall make such information available to the historic and design review commission for review and recommendation as to significance. If the historic and design review commission concurs in the significance, the historic and design review commission shall recommend that the building, object, site, or structure be designated as a historic landmark. Following such determination, the applicant may request a demolition permit by following the procedures for historic landmarks or properties within a historic district as prescribed in this section.

    (e)

    Approval Criteria. See article VI, section 35-614 of this chapter.

    (1)

    Historic Landmark. Should the applicant for a certificate regarding demolition of a historic landmark satisfy the historic and design review commission that he will suffer an unreasonable economic hardship if a demolition permit is not issued, or, in failing to demonstrate unreasonable economic hardship, the applicant demonstrates loss of significance which dictates demolition of the significant historic landmark, the historic and design review commission shall recommend approval of a certificate for the issuance of a demolition permit.

    (2)

    Contributing Property. Should the applicant for certificate regarding demolition of a contributing property in a historic district satisfy the historic and design review commission that he will suffer an unreasonable economic hardship if a demolition permit is not issued, or, in failing to demonstrate unreasonable economic hardship, the applicant demonstrates loss of significance which dictates demolition of the property, the historic and design review commission shall recommend approval of a certificate for the issuance of a demolition permit.

    (3)

    Property Deemed to be an Intrusion Into the District. In those cases in which the historic and design review commission finds that a building, object, or structure proposed for demolition is located in a historic district, but is considered an intrusion in the district, the historic and design review commission shall reaffirm the evaluation of the resource as an intrusion using criteria set forth in this article prior to recommending approval of a certificate regarding demolition. When the resource is determined to be an intrusion, the historic and design review commission shall not recommend approval of a certificate regarding demolition unless the property owner agrees to minimum landscape and maintenance requirements as specified under sections 35-615 through 35-616 and all other city ordinances and codes. In any event, when the historic and design review commission recommends approval of such certificate, demolition permits for buildings, objects, sites, or structures in historic districts shall not be issued until all plans for the site have received approval from all appropriate city boards, commissions, departments and agencies.

    (f)

    Subsequent Applications. (See subsection 35-451(f) of this chapter.)

    (g)

    Amendments. (See subsection 35-451(g) of this chapter.)

    (h)

    Scope of Approval.

    (1)

    Other Agency Approval Required. When the historic and design review commission recommends approval of a certificate regarding demolition of buildings, objects, sites, or structures in historic districts, permits shall not be issued until all plans for the site have received approval from all appropriate city boards, commissions, departments and agencies.

    (2)

    Replacement Plans. Following recommendation for approval of demolition, the applicant must seek approval of replacement plans consistent with the criteria set forth in sections 35-609 to 35-613 prior to receiving a demolition permit and other permits. Replacement plans for this purpose shall include, but shall not be restricted to, project concept, preliminary elevations and master development plans, and completed working drawings for at least the foundation plan which will enable the applicant to receive a permit for foundation construction. Applicants that have received a recommendation for a certificate and approval of required replacement plans shall be permitted to receive such demolition permit without additional historic and design review commission action on demolition, following the posting by the applicant of a performance bond and a payment bond in an amount sufficient to cover all construction costs and to inure to the benefit of the City of San Antonio. If a contractor has been selected, then the bonds may come from the contractor and shall inure first to the benefit of the City of San Antonio, second to the benefit of the developer.

    (3)

    Certificate for New Construction. Applicants that have received an approval of a certificate regarding demolition shall be permitted to receive a demolition permit without additional historic and design review commission action on demolition, following the historic and design review commission's recommendation of a certificate for new construction. Permits for demolition and construction shall be issued simultaneously if requirements of section 35-609, new construction, are met, and the property owner provides financial proof of his ability to complete the project.

    (i)

    Recording Procedures. (See subsection 35-451(i) of this chapter.) Applicants that have received a recommendation for a certificate for demolition of a historic landmark shall document buildings, objects, sites or structures which are intended to be demolished with 35mm slides or prints, preferably in black and white, and supply a set of slides or prints to the historic preservation officer. Applicants shall also prepare for the historic preservation officer a salvage strategy for reuse of building materials deemed valuable by the historic preservation officer for other preservation and restoration activities.

(Ord No. 98697 § 4 and 6) (Ord. No. 2010-06-24-0616, § 2, 6-24-10) (Ord. No. 2010-11-18-0985, § 2, 11-18-10; Ord. No. 2015-12-17-1077 , § 2, 12-17-15; Ord. No. 2017-10-05-0756 , § 1(Att. A), 10-5-17; Ord. No. 2017-12-14-1010 , § 2, 12-14-17)