§ 35-703. Newly Annexed Territory.  


Latest version.
  • Nonconforming rights may be granted to newly annexed areas in accordance with the following provisions and upon payment of the fees specified in Appendix "C." All applications for nonconforming rights must be filed within sixty (60) days of the effective date of annexation.

    (a)

    Incomplete Construction. Construction may be completed on any structure legally under construction upon annexation provided:

    (1)

    The owner or his designated representative applies to the director of planning and development services for a permit to authorize further work on the structure stating the proposed use of the structure and attaching thereto the plans and specifications relating to the construction; and

    (2)

    The construction is completed within two (2) years of the effective date of annexation.

    Action on the permits shall be taken by the director of planning and development services within fifteen (15) days from the date of application. The director shall deny the permit if he finds that the construction will not meet the requirements of the building, fire protection, or minimum housing codes and other applicable ordinances and codes of the city. If the permit is refused, the construction work shall cease until necessary corrections are made.

    (b)

    Proposed Construction. Proposed construction may be completed upon a finding by the zoning commission that sufficient evidence exists that planning for the proposed use was in progress prior to annexation, as prescribed by Appendix "B" to this chapter. Within fifteen (15) days from the date of such filing, the director shall present the evidence to the zoning commission for their determination, unless the applicant agrees to a longer period. The applicant shall have twelve (12) months from the date of the zoning commission's favorable determination to secure all building permits. After that time, the nonconforming rights shall expire.

    (c)

    Master Development Plans. Newly annexed areas may be entitled to nonconforming rights for a master development plan upon favorable consideration by the zoning commission. The property owner must submit an application as prescribed by Appendix "B" of this chapter. The zoning commission shall conduct a public hearing on the nonconforming rights master development plan after giving notice to the owners of property within two hundred (200) feet in the manner provided in section 35-403 for a rezoning. The purpose of the public hearing shall be to ascertain (1) the extent to which development of the master development plan had progressed prior to annexation and (2) the extent to which the master plan complies with the policies and objectives of the city's land use plan. If the zoning commission approves the master development plan, construction in conformance with the plan must begin within one (1) year, with all portions of the plan either completed or under construction within five (5) years from the date of annexation. After that time, the nonconforming rights shall expire.

(Ord. No. 98697 §§ 4 and 6)(Ord. No. 100126)